B&S Group successfully delivered two fully completed substations—one High Voltage (HV) and one Low Voltage (LV)—for our client, Powersystems. Designed, built, and commissioned at our Chester facility, each unit (14.7m x 3.9m) was transported with a police escort and arrived safely at Coylton-Greener-Energy Park BESS in Ayr.
These substations form a vital part of Statkraft Greener Grid Parks, which use smart technology in compact buildings to enable more renewable energy to flow through the national grid. This project directly supported the UK’s mission to build a cleaner, greener, and more resilient energy system.
👏 Huge credit to the B&S Group team for their expertise, hard work, and seamless safe delivery—another step forward in powering a greener future. 💚